Feature Profiles
Wesley to Miekle Transmission Project
Construct 82 km of 230-kV double-circuit transmission line and two-bundle Hawk ACSR. Valard overcame a short timeline and logistical difficulties to successfully construct 55 km of the line over an 84-day winter work window...

BP Noel
Design, procure and construct 67 km of 138-kV single-circuit transmission line on wood pole structures. The scope included all engineering, procurement, construction, planning and scheduling, surveying, labour, materials, equipment, supervision, tools, transportation and supplies...

Herblet to Ralls Island Line
Construct 168 km of 230-kV single-circuit transmission line in Manitoba. This involved the construction of access, foundations, tower assembly and erection and stringing of the conductor...

Clowhom Transmission Project
Supply and construct approximately 34 km of 138-kV transmission line and fibre optic communications cable to connect two run-of-the-river hydro plants to an existing BC Hydro substation. This involved constructing two transmission lines, each built to a different standard...

Carmacks to Stewart Transmission Line Phase I and II
In Phase I of the project, Valard constructed 100 km of 138-kV transmission line and 30 km of 25-kV distribution line to the Minto Mine. This involved a 450 m crossing over the Yukon River and a 650 m crossing of Tatchun Creek...

Kemess Mine
Construct a 190-km, 230-kV transmission line deep in the McKenzie Forest District. Valard was responsible for road and right of way maintenance, material management, foundations through rock, helicopter stringing, structure setting, conductor installation and cut over...