PWR | $21.66 | -0.35Volume: 2386537
TwitterFlickr
Feature Profiles

Wesley to Miekle Transmission Project

Construct 82 km of 230-kV double-circuit transmission line and two-bundle Hawk ACSR. Valard overcame a short timeline and logistical difficulties to successfully construct 55 km of the line over an 84-day winter work window. This portion of the project went through environmentally sensitive areas, where Valard took extra measures to mitigate any negative impacts. The balance of the line was completed with a smaller crew follow a two-month hiatus for spring break-up.

This project was successfully completed on budget, on time and without incident as a joint venture with the Woodland Cree First Nation.

Client: ATCO Electric
Location: Peace River, Alberta
Dates: January to September 2010
Services: Construction

BP Noel

Design, procure and construct 67 km of 138-kV single-circuit transmission line on wood pole structures. The scope included all engineering, procurement, construction, planning and scheduling, surveying, labour, materials, equipment, supervision, tools, transportation and supplies.

The project was built over watersheds, rivers and through environmentally sensitive areas. Two major river crossings were completed with helicopter construction techniques. Helicopter construction was also required for other challenging terrain.

The project was completed within budget and to schedule without incident.

Client: BP Canada
Location: Dawson Creek, British Columbia
Dates: March 2009 to April 2010

Services: EPC

 

Herblet to Ralls Island Line

Construct 168 km of 230-kV single-circuit transmission line in Manitoba. This involved the construction of access, foundations, tower assembly and erection and stringing of the conductor.

Weather was not on the side of the project and provided unpredictable difficulties. A very mild winter during the first construction season caused a weak freeze-up that did not last long. By mid-winter, crews were facing major melts that caused considerable problems with right of way access and equipment. Then, severe blizzards hit and buried access roads, equipment and materials in deep snow.

Other challenges related to the terrain of the project. The length of the line spanned over wetland and Canadian Shield rock. Access proved difficult, as there were swamps in some areas that ran up to 12 km long and 60 ft deep. This required a combination of challenging foundations and specialized foundation equipment to get through the swamp and drill into the rock bed below. In addition, Valard set 145 structures by helicopter over the Canadian Shield terrain in order to successfully meet a tight schedule.

The project was completed in the short duration of the schedule, on budget and without incident.

Client: Manitoba Hydro
Location: The Pas, Manitoba
Dates: December to March 2009 and 2010
Services: Construction

 

Get Adobe Flash player Install latest flash player if you can't see this gallery, or click here to see the html version.

Clowhom Transmission Project

Supply and construct approximately 34 km of 138-kV transmission line and fibre optic communications cable to connect two run-of-the-river hydro plants to an existing BC Hydro substation. This involved constructing two transmission lines, each built to a different standard.

This project was built over very difficult terrain, and Valard assisted in the redesign of several sections. Some sections of the line that were accessible only by foot or helicopter required challenging hand construction and significant amounts of blasting. The line also ran through several avalanche areas and sensitive watersheds and rivers.

Valard was responsible for project management, planning and scheduling, design consulting, procurement and construction. The project was completed successfully to the client’s timeline and budget.

Client: Canadian Projects/HydroMax
Location: Clowhom, British Columbia
Dates: January to August 2009
Services: Procurement and construction

Get Adobe Flash player Install latest flash player if you can't see this gallery, or click here to see the html version.

Carmacks to Stewart Transmission Line Phase I and II

In Phase I of the project, Valard constructed 100 km of 138-kV transmission line and 30 km of 25-kV distribution line to the Minto Mine. This involved a 450 m crossing over the Yukon River and a 650 m crossing of Tatchun Creek. The project was constructed under a five-way joint venture agreement with three local First Nations communities and a local contractor. In Phase II, Valard constructed an additional 67 km of 138-kV line through permafrost.


The project was logistically challenging due to the geographical remoteness of the work. Also, 22 structures associated with the line were in an environmentally sensitive area that required any excavation to be done by hand.

Client:
Yukon Energy Corporation
Location: Klondike Region, Yukon
Dates: March to September 2008
Services: Procurement and construction

Get Adobe Flash player Install latest flash player if you can't see this gallery, or click here to see the html version.

Kemess Mine

Construct a 190-km, 230-kV transmission line deep in the McKenzie Forest District. Valard was responsible for road and right of way maintenance, material management, foundations through rock, helicopter stringing, structure setting, conductor installation and cut over.
This was the first major private transmission line in Canada and proved Valard’s ability to overcome any logistical complexities. The project was constructed in extremely difficult and remote mountain conditions, through sensitive wetlands, high alpine areas, avalanche areas and snowfalls up to 15 ft. It required the purchase of several large excavators for the installation of subterranean bearing pads on all structures and anchors. Helicopter construction techniques were also needed on much of the mountainous terrain.

The project was completed to schedule over a ten-month timeline, without incident and within budget.

Valard was also responsible for providing camp accommodations for crews and the client’s staff. As well, two full-time EMTs were provided for the duration of the job.

Client:
Royal Oak Mines
Location: North-central British Columbia
Dates: 1997-1998
Services: Construction

Get Adobe Flash player Install latest flash player if you can't see this gallery, or click here to see the html version.