/ Two parallel 315 kV alternating current (AC) transmission lines

The project was 490.4 km in length from Muskrat Falls Hydroelectric Generating Facility to the electricity infrastructure at Churchill Falls

Some key features of this project are:

  • 1,271 towers installed - including 1,001 guyed structures & 270 self-supporting structures
  • 3,211,022 bolts were used to install 11,896 metric tons of steel
  • Crews installed 2,081 foundations and 4,364 anchors
  • The total length of conductor installed was 6,296.7 km
  • There were 889 staff working on the project for a total of 1,155,452 labour hours
Back to Project List

/ Client

Nalcor Energy

/ Start Date

Jan
2014

/ End Date

Jun
2016