Electric Power

Labrador-Island Link Transmission Line

350 kV Overhead High-Voltage Direct Current (HVDC) Transmission Line

This project was 1,092 km in length, connecting the Muskrat Falls Generating Facility in central Labrador to Soldiers Pond on Newfoundland’s Avalon Peninsula. Completing this project was a massive achievement. We could not have reached this point of completion without the dedication and commitment of all our staff. Many of which were hired locally.

Client

Nalcor Energy

Start Date

September 2014

End Date

November 2017

Highlights
  • 3,223 towers installed - 2,841 guyed structures & 382 self-supporting structures
  • 8,667,616 bolts used to install 34,093 metric tons of steel
  • 4,369 foundations and 11,364 anchors
  • 2,964.4 km of conductor installed
  • 1,446 staff working on the project for a total of 4,172,806 labour hours
We Can Make Your Next Project Easier

Recent Projects