/ 115 kV to 66 kV Project

  • Valard completed the overhead and electrical construction of the Manigotagan Corner Station.
  • The first phase of the project consisted of the civil work, while the second phase included all electrical assembly and installation.
  • The project also included the installation of 1 Control Building and 1 – 120 foot Communication Tower.
  • The area of the site development was 15,958 m2.
  • The project was completed 6 weeks ahead of the contract completion date.
Back to Project List

/ Client

Manitoba Hydro

/ Start Date

Oct
2016

/ End Date

Apr
2017