Electric Power

Hydro One Bruce x Milton

Major Milestone

We had an incredible group of people working on Bruce-to-Milton, and their efforts definitely made this project a huge success. Valard’s services included planning and scheduling, project management, structure assembly and erection, and conductor stringing.

Client

Hydro One

Start Date

August 2010

End Date

August 2012

Highlights
  • 720 steel lattice towers weighing approximately 26,000 tonnes were built
  • 4,700 kilometres of conductor were strung and energized
  • Included crossings of approximately 100 roads, several railroad tracks, and environmentally sensitive areas
  • Crossing three major roadways
  • Working inside Bruce Nuclear power plant
  • Working through the Niagara Escarpment